NTIA issued new General Terms and Conditions dated November 2025 that include dozens of changes to the BEAD rules for recipients, but also changes that impact state Broadband Offices that have wider implications on States. I’m not listing all of the changes here, but there is a great summary of the changes done by the Benton Institute on January 14. This blog will look at the issues related to permitting that have repercussions far outside of the BEAD grant recipients.
In Section 13.D of the revised NTIA Terms and Conditions, State Broadband Offices (SBOs – which are described as Grantees by the NTIA) have a lot of major new obligations related to permitting.
SBOs must “establish procedures to ensure that broadband-related permit applications are promptly accepted, and requests are approved or denied within 90 days”.
In general, SBOs don’t hold a position of authority in State governments to impose rules on anybody other than recipients of grants. Permits for BEAD will mostly mean getting permits to build along existing roads. SBOs are going to have to agree to this requirement, but it’s hard to imagine how an SBO can impose rules for State roads, County roads, Township roads, Municipal roads, roads through Tribal lands, and the biggest challenge – roads passing through federal lands. The goal of getting permits completed within 90 days is great, but it’s hard to think that the small number of people working in SBOs even know the identity of the many permitting authorities in a state, let alone can have any influence, other than perhaps begging, to get BEAD permitting authorities to meet the 90-day deadline. An even bigger challenge is permitting on private land, since a lot of rural roads are privately owned. What can an SBO possibly do to influence private permits?
SBOs must assist “state and local authorities in establishing a single, dedicated point of contact, which has knowledge of the application and review processes, for broadband-related permits.
The key word in this requirement is ‘assist”. Assuming that States even want to go through this process, they vary widely in how this would be achieved. There are States where a Governor might be able to do this. There are States where a State Regulatory Commission might have the authority to tackle this. But in many States, this might require action for a Legislature. What happens in States that don’t undertake the formation of a single, dedicated point of contact?
SBOs must provide technical assistance to permitting agencies to ensure sufficient capacity (e.g., Master Agreement and Consultant Reimbursement Agreement templates, surge support for permit processing, etc.)
This recognizes that local governments often will not have enough staff to quickly process all of the permits required by a BEAD project. SBOs must develop template contracts that can assist a locality if it wants to get help to speed up permitting. But this doesn’t address the issue and time required by local governments when hiring outside vendors. It doesn’t address if a local government has a budget for additional help. Interestingly, this extra funding could come in some states from BED nondeployment funds, assuming there is enough such funding for the purpose.
SBOs must provide “deference to the construction techniques chosen by BEAD Subgrantees (without seeking to influence those decisions), absent any identified safety concerns.
I don’t know if anybody, except perhaps for big ISPs that might have suggested this language to NTIA, really knows what this means, other than allowing construction practices that would otherwise not be allowed by pole owners or by the governments who control the rights-of-way for buried construction. SBOs are being directed to turn their heads to what would normally be non-compliant construction techniques. I’m not sure how pole owners and rights-of-way owners will be expected to comply with this.
SBOs must maximize “streamlined processing through permitting by rule; batch processing of substantially similar permit requests; and waiving or expediting duplicative or burdensome broadband permitting requirements where possible.”
SBOs can certainly promote language that allows batch processing. But, related to the staffing issue addressed earlier, how might a County with little or no staffing be expected to comply with big batches of permits? Even more confounding, are SBOs expected to look at local rules for permitting across the state to identify the ones that are duplicative or burdensome – and what do they do when they identify such rules?
SBOs must follow “FCC rules regarding timelines, rates, terms, and conditions for access to municipally owned poles and conduit for broadband projects – including provisions in the FCC’s rules providing for “one-touch make-ready” and “self-help” – and requiring BEAD Subgrantees that own poles (including cooperatives) to comply with FCC rules across their footprint.”
Around 23 states and D.C. have decided to have their own pole attachment rules, something that has been allowed by federal legislation. While most of these rules are largely the same as the FCC rules, many differ in substantive ways. How can an SBO in a state with its own pole regulation somehow force the State to suddenly follow the FCC rules. The specific requirement cites self-help and one-touch make ready, which are some of rules where States have taken a decidedly different stance than the FCC.
Overall impression of these requirements. SBOs will clearly try to follow these requirements since they must agree to them before they get BEAD funding. But these rules create huge problems for SBOs that don’t have the authority and muscle to impose these rules on the rest of the State and on the many entities that are involved in permitting. To some degree, the severity of these rules, when judged against the practical chance of an SBO accomplishing them, seems like a tool for NTIA to be able to say that any selected State has failed its obligations. I assume that if NTIA tries to withhold funding to a State based on these rules that it will be sued, but that means BEAD goes on hold in that State, to the detriment of the many rural residents relying on better broadband. Interestingly, none of these rules hinders satellite BEAD winners.